bio - technology park Luckenwalde - TGZ II 1 – 2 section of construction


  back forward  
 
re - construction of technological and foundational center / Brandenburg
Luckenwalde
   
laboratorial and measurement rooms for bio - chemical and sanitation rooms and human medicine
laboratorial and measurement rooms laboratorial and measurement rooms
 
planning of the complete technical out - fitting by Passau engineers Dessau
complete floor surface area : 5090 sq.m.
construction costs : 5.275.000,00 EUR
re - construction and renovation of bio - technical center with laboratorial rooms for bio - technical, cooling & storage rooms for solvents and sanitation rooms and human medicine
   
sanitary and heating installation installation of ventilation
sanitary and heating installation installation of ventilation
 
bio - technology park Luckenwalde excerpt of laboratory equipment